InvestmentsGlobal RaceGoogle agreed on October 6 to buy 890 MW of new nuclear output from Constellation under a 20-year contract, which Yahoo Finance reported at $4.3 billion. The money pays for uprates at 11 existing reactors. One week earlier, Amazon signed a 20-year agreement with Constellation covering 690 MW from Calvert Cliffs in Maryland, including a 190 MW uprate due between 2030 and 2032. Together the pair backs roughly 1,080 MW of added capacity at plants that are already licensed and already on the grid.
Neither deal involves a small modular reactor. That is the useful fact. Big Tech’s nuclear spending is real and growing, but it lands first where licenses, interconnections and operating crews already exist. The reactors that give this sector its name sit further back in the queue, and the stock market has started to price that in.
Uprates and restarts get the cash first
Meta set the template in January. It announced agreements covering up to 6.6 GW by 2035, and World Nuclear News detailed the Vistra piece: 20-year PPAs for 2,176 MW from the operating Perry and Davis-Besse plants in Ohio, plus output from 433 MW of uprates at those sites and Beaver Valley in Pennsylvania. Microsoft’s 20-year deal with Constellation is the other anchor. It funds the restart of Three Mile Island Unit 1 as the Crane Clean Energy Center, about 835 MW, and Constellation now targets 2027, a year ahead of the original 2028 date.
Washington is adding balance-sheet support. TechCrunch reported on October 28 that the Department of Energy offered Constellation a conditional loan commitment of up to $5 billion for uprates at eight plants. Constellation has said it committed more than $7 billion to add 1,080 MW for Google, Amazon and Meta. The word to watch is conditional. A loan offer is not a closed loan, and an uprate is not megawatts on the grid.
The Calvert Cliffs deal also carries a siting lesson. AWS had planned seven data center buildings on roughly 2,000 acres beside the plant and dropped the plan after resident opposition, according to Maryland Matters as relayed by Baxtel. Amazon could not build next to the reactor, so it bought the reactor’s growth. In that market, zoning fights set schedules more reliably than megawatts do. When you read a developer’s pipeline, ask whether its power is contracted or only hoped for.
The SMR commitments are real but early
The new-build deals are funded in part and permitted in part. They are not operating. Here is where the main ones stand:
Kairos Power, TVA and Google: TVA will buy up to 50 MW from the Hermes 2 plant in Oak Ridge, Tennessee, the first utility PPA for a Generation IV reactor. Power is due by 2030, and the NRC issued a construction permit in November 2024. It is the first deployment under Google’s 500 MW by 2035 agreement.
Amazon, X-energy and Energy Northwest: The Cascade Advanced Energy Facility near Richland, Washington, would use Xe-100 reactors, each 80 MWe and high-temperature gas-cooled. The first phase is four modules totaling 320 MW of a planned 12. X-energy’s SEC filing targets a construction permit application by the end of 2026, with construction by the end of the decade.
Meta and TerraPower: Funding for two Natrium units, a 345 MWe sodium fast reactor with molten salt storage, within a possible eight-unit program totaling 2.8 GW plus 1.2 GW of storage.
Meta and Oklo: A 1.2 GW campus in Pike County, Ohio, with Meta prepaying for power. The first phase is targeted for as early as 2030.
The Oklo line needs the sharpest calibration. The NRC’s own page still lists the Aurora powerhouse in pre-application activities, and the agency denied Oklo’s 2020 application in January 2022 without prejudice for failing to supply information. A prepayment from Meta is a commitment from a buyer. It is not a license.
Every project, deal, company, and regulatory event we cover is logged, verified, and searchable in SMRbrief Pro, which is how we separate an announcement from a permit when the headlines blur them together.
Why the contracts look the way they do
The common structure is a long PPA that gives the plant owner revenue certainty. Vistra said the Meta agreements let it pursue 20-year license renewals at each reactor. Constellation says the same of Amazon and Calvert Cliffs. Calvert Cliffs power keeps flowing into PJM, the regional grid, as it does today. That front-of-meter design lets a hyperscaler pay for new generation without pulling it off the system.
There is a regulatory reason for that choice. FERC rejected an expanded co-location arrangement at Talen’s Susquehanna plant in November 2024, and its later order directed PJM to create new transmission options for co-located load. Grid-connected contracts avoid most of that fight. The trade-off is that the data center still draws from the same grid, so the clean claim is an accounting one more than a physical one. Reasonable people can disagree on whether that matters. Readers who follow utility regulation should watch whether state commissions begin to.
Delivery risk sits with the sellers. Data Center Frontier noted that neither the federal commitment nor Meta’s electricity contracts guarantee the capacity arrives on schedule. That is an accurate reading.
What it means for a portfolio
The market has already separated the cash-flowing owners from the pre-revenue developers. Constellation shares rose more than 12% on the Google news and closed at $239.65 on November 5. Vistra gained 10.5% on the day Meta announced its deals.
The developers tell a different story. In early October, Oklo traded near $35 against a 52-week high of $193.84, a market value of about $6.8 billion. NuScale traded near $7.32 against a high of $57.42, about $3.1 billion. NuScale holds the only NRC-approved SMR design in the United States, a 77 MWe module. Oklo holds no NRC license. Both stocks fell even as hyperscaler nuclear commitments grew, which suggests investors are no longer paying for announcements alone.
My read is that the first dollars from Big Tech accrue to owners of operating fleets, because those owners can deliver within a decade. SMR developers must still clear licensing, financing and first-of-a-kind construction, and the sector’s cost record is poor. The Motley Fool cites an average overrun above 100% for new reactors. None of this is investment advice. It is a case for tagging every position by milestone: announced, contracted, permitted, under construction or operating.
When the first Cascade or Natrium unit slips a year, which contract says who pays for the delay?