Every SMR pitch deck opens the same way: smaller reactors, built in factories, stamped out like Toyotas instead of hand-carved like cathedrals. š° Cheaper by design, faster to build, easier to finance. Itās a great story, and parts of it are even true. But the nuclear industry has a long, expensive habit of promising one number and delivering a very different one, and the SMR wave so far hasnāt broken that habit. š Here are five real dollar figures, not projections, not vendor slide-deck math, that show what building one of these things actually costs right now.
The number that punctured the hype
$9.3 billion. Thatās what NuScaleās flagship US project, the Carbon Free Power Project in Idaho, was projected to cost by the time it collapsed in November 2023, up from an original $5.3 billion estimate just two years earlier. A 75 percent jump in construction cost pushed the target power price from $58 to $89 per megawatt-hour, and thatās before accounting for inflation between now and whenever the plant would have actually opened. š The Utah utilities that had signed up for the power backed out, subscriber by subscriber, until there werenāt enough left to justify finishing it.
Hereās the number that really stings: once you divide that final $9.3 billion by the plantās planned 462 megawatts, NuScaleās project worked out to roughly $20,139 per kilowatt, according to IEEFAās analysis of the cost estimate. Thatās essentially the same price per kilowatt as the infamously over-budget Vogtle expansion in Georgia, the very poster child for large nuclearās cost problems that SMRs were supposed to fix. If the factory-built promise canāt beat the thing itās replacing on a dollar-per-kilowatt basis, what exactly is the pitch? š¤
A few reasons that estimate ballooned so fast:
Commodity and steel prices climbed sharply between 2021 and 2023
Interest rates used in the projectās financing model rose roughly 200 basis points
The project shrank from twelve modules to six, losing economies of scale it was counting on
Licensing, safety review, and quality assurance costs kept adding years and dollars
The baseline these projects are trying to beat
To be fair to SMR developers, large nuclearās own track record isnāt exactly a high bar to clear. š Vogtle Units 3 and 4 in Georgia, the only new nuclear reactors completed in the US in the past three decades, were originally priced at $14 billion. By the time Unit 4 finally came online in 2024, seven years late, the total had climbed past $34 billion, according to Wikipediaās detailed construction history. Thatās more than double the original number, on a project built by an experienced utility with federal loan guarantees behind it. šļø
The Vogtle math, in the numbers that actually moved:
$14 billion: the original 2008 estimate for both new reactors
$25 billion: the revised total by 2018, after Westinghouseās bankruptcy
$34 billion: the final tally once Unit 4 entered service in 2024
7 years: how far behind schedule the project ultimately ran
This is the real comparison SMRs need to win, not against solar or wind, but against the nuclear industryās own history of blown budgets. And so far the early data suggests SMRs are inheriting the same disease rather than curing it. šø Have you noticed how every big infrastructure story eventually turns into a story about who pays for the overrun?
The one real number instead of a promise
Not every SMR cost figure is a cautionary tale. šļø GE Hitachiās BWRX-300 is actually under construction right now at Ontarioās Darlington site, and its current price tag is a real, audited estimate rather than a vendor projection. As of May 2025, the project was estimated to cost at least CAD $7.7 billion, working out to roughly ā¬15,870 per kilowatt, per analysis from the Heinrich Bƶll Foundationās Brussels office. Thatās still expensive by any normal standard, but itās a number attached to concrete actually being poured, not a slide in an investor deck. šµ
That distinction matters more than it sounds. A project with:
A signed construction contract and a utility actually pouring foundations
Regulatory approval already secured rather than pending
A single owner (Ontario Power Generation) absorbing the financial risk
A real, if painful, price tag instead of an aspirational one
is simply a different category of investment than one still selling subscriptions to future power. š If you want the underlying financials tracked deal by deal instead of piecing them together from press releases, SMRbrief Pro keeps a running ledger of what every active project actually costs versus what it originally promised.
The gap that supposedly closes with scale
Hereās the number every vendor is betting the whole business model on: todayās first-of-a-kind (FOAK) SMRs run somewhere between $80 and $150 per megawatt-hour, while vendors promise that Nth-of-a-kind (NOAK) production, once a design has been built dozens of times, drops that to $50 to $80 per megawatt-hour. ā” The Department of Energy has floated an even more optimistic long-run figure of around $60/MWh if designs get standardized and mass-produced. š
The catch is how many units it actually takes to get there. Industry estimates suggest the cost curve doesnāt flatten out until somewhere between 5 and 7 identical units, or 10 to 20 gigawatts of installed capacity, based on techno-economic modeling published through the Department of Energy. South Korea needed to build 24 nearly identical reactors before it saw meaningful cost reductions on its fleet. š
Right now, the field looks like this:
NuScale: light-water design, one canceled US project, pursuing Romania and Poland instead
TerraPower: sodium-cooled Natrium, one unit under construction in Wyoming
X-energy: high-temperature gas design, backed by Amazon, still pre-construction
GE Hitachi: BWRX-300, the only design actually pouring concrete, in Canada
Five different designs, five separate learning curves, and not one of them has built a second unit yet, let alone a fifth. š¢
So the real number that matters isnāt $60 or $80 or $150 per megawatt-hour. Itās the number of identical reactors any single company needs to actually build before its own promised price shows up on a customerās bill, and right now that number is closer to zero than anyone in the industry likes to admit. Which of these five numbers would you want written into a power contract before signing it?



