EnergyGridTerraPower started construction on Kemmerer Unit 1 on April 23, a 345 MWe sodium-cooled Natrium reactor with a project cost of up to $4 billion and a 2030 completion target. It stands beside PacifiCorp’s Naughton coal plant in Wyoming. The company has called it the only coal-to-nuclear project under development, and that claim depends on how loosely you define the term.
Naughton is not dead. Its coal units are being converted to gas, and the reactor sits on a greenfield site next to the plant. The projects that actually occupy cleared coal sites are further behind. Reading them together shows what a coal site gives a reactor developer and what it does not.
What the coal site is worth
The best-known estimate is a 2022 study by three national laboratories for DOE. It screened sites and identified 157 retired and 237 operating coal plant sites as candidates, with 80% judged suitable for advanced reactors. It also estimated 15% to 35% lower overnight construction cost, for a modeled 1,200 MWe coal plant replaced by 924 MWe of nuclear. The savings come from reused transmission lines, switchyards, cooling ponds or towers, roads and buildings.
Treat that figure as a model from 2022, not a measured result. DOE said further investigation was needed on plant ownership and the condition of the remaining infrastructure. Note also what the list leaves out. The reusable assets are the grid connection, the land and the civil works. The boiler is not on it.
Five projects, five stages
Kemmerer Unit 1, Wyoming (under construction): The NRC voted on March 4 to issue the construction permit, which DOE called the first for a commercial non-light-water reactor. DOE is cost-sharing up to $2 billion of the cost. TerraPower still needs a separate operating license.
Doicești, Romania (investment decision taken, conditions unmet): The site held a decommissioned 600 MW coal station. Nova Power & Gas demolished it, removed about 600,000 tonnes of material and upgraded a 650 MW grid connection. The planned plant is a NuScale six-module VOYGR-6, 462 MWe in total.
Cottam, England (proposal): Holtec and EDF submitted a joint proposal on June 23 for up to four SMR-300 units, about 1.3 GW, on a coal station site decommissioned in 2019. They would use the existing grid infrastructure.
Belews Creek, North Carolina (site permit under review): Duke Energy filed an early site permit application on December 30, 2025. The 1,000-acre site sits beside an existing coal and gas plant and the permit would allow up to 2,250 MW.
Tušimice and Dětmarovice, Czechia (memorandum): ČEZ named these coal sites as preferred locations for its second and third SMRs under a memorandum with Rolls-Royce SMR. A memorandum binds no one to build.
Duke’s timing is the most candid. It targets the first SMR in 2036 and 600 MW by 2037, and it chose a technology-neutral permit so it can pick among six designs later. Its approval is expected around 2027. The plant it would sit beside is scheduled to retire in the late 2030s, so Belews Creek is a successor project and not a conversion of a dead plant.
The cleared site that has not become a plant
Doicești is the best test of the coal-site thesis, because the site work is done. On February 12, Nuclearelectrica’s shareholders approved a final investment decision, and the project company would buy only the first of six modules, paying for the rest after it is proven. The conditions attached to that decision were shared with investors under an eight-year confidentiality agreement and were never published.
On July 15, shareholders including the Ministry of Energy voted down a proposal to benchmark other SMR technologies. Nuclearelectrica said some of the investment decision’s conditions could not be met for reasons outside its control. NuScale said it continues to work to satisfy them. A decision with unmet conditions is not a construction start. Anyone treating “FID” in a headline as the finish line should read this case twice.
What reuse does not fix
A grid connection trims site cost and interconnection time. It does nothing for the first-of-a-kind reactor, the fuel or the financing. Simple division on Kemmerer’s figures gives about $11,600 per kW, and that is for a design with federal cost-sharing. Natrium also needs high-assay low-enriched uranium, a fuel in short supply domestically, and TerraPower already announced a delay in late 2022 for that reason. Doicești has the site and the connection and still lacks agreed commercial terms for the modules.
The coal site solves the problem a utility understands best. It does not solve the problems that decide whether the reactor gets built.
What to watch next
Four dates matter. The NRC’s decision on Duke’s Belews Creek permit, expected around 2027. The UK government’s response to the Cottam proposal. Whether Romania’s shareholders and NuScale close the gap on Doicești’s conditions. And TerraPower’s operating license application, which is the step between a permitted plant and a running one. Readers following a specific coal-site project should check which of these it is waiting on.
Because these projects sit at five different stages, a record that captures the stage matters more than the announcement. Every project, deal, company, and regulatory event we cover is logged, verified, and searchable in SMRbrief Pro, and that discipline is the main defense against calling a memorandum a plant.
If the grid connection is the real asset, should utilities be paid to keep switchyards intact at coal plants they are about to demolish?