InvestmentsRegulationThe NRC issued the Tennessee Valley Authority a construction permit on September 29 for a 300 MWe BWRX-300 at Clinch River, Tennessee. The review took 14 months, four months ahead of the agency’s own schedule. The permit does not authorize operation, and TVA has announced no construction date. The gap between that headline and a reactor producing power is the subject of this piece.
The sequence below follows the US process, with Canada and the UK as cross-checks. Each step is tied to a real project and a real date.
Steps 1 to 3: pre-application, pathway and design review
Step 1 is pre-application engagement. It is unglamorous and it decides the schedule. TerraPower filed a 14,000-page construction permit application in March 2024, and CEO Chris Levesque said it was the product of years of pre-application work with NRC staff. Oklo shows the other case. It completed the NRC’s Phase 1 readiness assessment for its Aurora combined license application in July 2025 with no significant gaps found, but the NRC’s own page still lists audits and a topical report under review. Oklo holds no NRC license, and the agency denied its 2020 application without prejudice in January 2022.
Step 2 is choosing a pathway. The NRC’s Part 53 rule took effect on April 29, 2026. It is an optional, technology-inclusive framework and the first new reactor licensing rule since Part 52 in 1989. Developers now choose among Parts 50, 52 and 53. Every project discussed in this piece applied before Part 53 existed. TerraPower’s Natrium, Dow’s Long Mott and TVA’s Clinch River all sit under Part 50, so Part 53 has not yet been tested on a full commercial review.
Step 3 is design review. NuScale’s US460 received an NRC standard design approval in May 2025 for a 77 MWe module, with six modules giving 462 MWe. The NRC accepted the application in July 2023 and finished two months ahead of schedule. An approval like this lets a utility reference the design, but it does not ensure a license. In Britain, the equivalent is Generic Design Assessment. Rolls-Royce SMR’s 470 MWe design entered Step 3 of three in July 2024, and the schedule called for completion in August 2026. I found no confirmation that the Design Acceptance Confirmation has been issued. Even then, the regulators state that the outcome does not guarantee a site licence.
Steps 4 and 5: the construction permit application and its review
Step 4 is docketing. The NRC checks that an application is complete enough to review, and the clock starts there. Dow’s Long Mott Energy subsidiary submitted its Xe-100 application on March 31, 2025, and the NRC accepted it on May 13. The proposal is four X-energy reactors at Seadrift, Texas.
Step 5 is the safety review, the environmental review and the hearing. Two federal measures now set the pace. The ADVANCE Act of 2024 requires hearings to finish within two years of docketing, and Executive Order 14300 caps decisions on new reactor applications at 18 months. The Natrium case shows the effect. The NRC began with a 27-month schedule for TerraPower’s Kemmerer Unit 1, then finished in 18 months after a streamlined mandatory hearing. The Commission voted on March 4, 2026, and DOE called it the first construction permit for a commercial non-light-water reactor. Natrium is a 345 MWe sodium-cooled fast reactor with molten salt storage.
Environmental review is where applicants can save the most time. On May 18, the NRC issued a finding of no significant impact for Long Mott. That is the first environmental assessment, rather than a full impact statement, for a Part 50 advanced reactor application. The NRC expects to finish the safety review later this year.
These are fast reviews by historical standards. They are also reviews of applications that took years to prepare. When you track a developer’s schedule, count from the first pre-application meeting and not from docketing.
Steps 6 and 7: building under hold points, then the operating license
Step 6 is construction under the permit. A permit allows nuclear construction and nothing more. Canada’s version makes the control points explicit. The CNSC issued Ontario Power Generation a licence to construct one BWRX-300 at Darlington in April 2025, after an October 2022 application and a two-part hearing. The licence runs to March 31, 2035, and it includes hold points where OPG must submit further information before work continues. A construction approval is a conditional one.
Step 7 is the operating license. In the US, this is a separate application. TerraPower must file one for Kemmerer before the plant can run, and the project is expected to finish in 2030. TVA needs one for Clinch River. A permit also does not commit the owner’s money. Dow has said it may not make a final funding decision on Long Mott until 2028, after it submits an operating license application. That is the clearest illustration of the difference between a permitted project and a financed one.
If you’re tracking the nuclear market professionally, SMRbrief Pro gives you the structured database to go deeper than any single article can. Whatever tool you use, record the step each project has actually completed and the date it did so.
The DOE track proves less than it appears to
A second route runs through the Department of Energy. Under the Reactor Pilot Program, four designs reached zero-power criticality at Idaho National Laboratory by July 4, 2026: Antares Nuclear’s Mark-0 on June 4, Valar Atomics’ Ward 250, Deployable Energy’s Unity, and Aalo Atomics’ Aalo-X on July 4. Deployable Energy came through a separate DOE pathway, the Nuclear Energy Launch Pad. Aalo says its next unit, 10 MW, will power an on-site data center in 2027.
That is genuine speed, and it is a different milestone. A zero-power test shows a core can sustain a chain reaction. It does not show a design can be licensed for commercial service, and DOE has described the program as a research effort meant to shorten the path to the NRC’s separate commercial licensing. The NRC proposed a rule on April 2 to streamline reviews of designs with a prior DOE or Department of War authorization, but I found no final version. Until one exists, the DOE track shortens the road without replacing it.
Which of the seven steps is your most important project actually on today, and who has verified it?